Tiffany Plaza – our new home

STUDIO RENTAL INFORMATION

STUDIO RENTAL INFORMATIONConveniently located in the Tiffany Plaza on Hampden Ave. in Denver, CO, Rocky Mountain Ballet Academy offers a 7,400 sq. ft. state-of-the-art facility near Interstate 25 and Downtown Denver. We have a welcoming lobby with a 65″ television for split-screen studio viewing and a warm-up area where dancers can prepare for class, audition or rehearsal. There is ample parking with Whole Foods, Target, Renaissance Hotel, Elvis Movie Theatre, Wells Fargo and several restaurants all in walking distance.  

Each studio offers:

– 14′ high ceilings
– Seamless Harlequin sprung floors  
– Temperature controlled atmosphere
– Viewing windows
– Professionally mounted barres with option for additional portable barres
– 9×6 mirror panels
– Cameras for lobby viewing 

Studio sizes: 

Blue studio: 1,600 sq. ft. ($50 per hour)
Yellow studio: 1,400 sq. ft. ($45 per hour)
Green studio: 1,200 sq. ft. ($40 per hour)
Pink studio: 900 sq. ft. ($35 per hour) 

Rental Availability

– Rehearsals 
– Auditions
– Master Classes
– Private Lessons (No ballroom or street shoes allowed. Tap shoes are allowed in the Pink studio, only). 

Lobby

Blue and Pink Studios

Yellow and Green Studios

THE MAKING OF A NEW STUDIO

November 28th, 2018, was our “ground-breaking” day! The hammer hit the walls for the first time as demolition began!  

On March 10th, 2018, our ballet studio was finished and we moved into our new home in the Tiffany Plaza in Denver, CO. This day was so exciting as we offered free master classes with RMBA faculty and Mrs. Era Jouravlev, Joffrey Ballet’s Ballet Trainee Program Director.  

March 8, 2018 – Our studios are ready for our Master Classes on Saturday! Let’s dance!

February 18, 2018 – The front entrance floors have been installed and the sprung floors are underway!

February 4th, 2018 – Jake hangs our speakers and the painting is nearly complete!

January 16th, 2018 – It’s almost time for floors and paint!

January 1st, 2018 – The drywall is going up!

December 21st, 2017 – Look at that framing!

December 14th, 2017 – The framing begins!

December 6th, 2017 – Demolition is nearing completion!

December 1st, 2017 – Just a few days in, but big changes have already happened!

November 28th, 2017 – Demolition begins!